Delays in the delivery of some long lead-time items have pushed back the expected restart of commercial production at Peninsula Energy’s Lance uranium projects in Wyoming, USA by up to three months to mid-2023.
Apart from the modest delivery delays, Peninsula says other aspects of the restart are progressing with capital expenditures in line with its DFS projections.
Limited scale wellfield operations have begun on one of the largest ISR uranium operations in the US, with first sales of new production still scheduled for the Dec qtr.